    • Storage thermal insulation construction schemeAccording to the thermal conductivity of XPS extruded insulation board 0.027 and storage requirements for temperature from-20 DEG, as the frozen library by using the following methods:
      First, the warehouse wall and roof insulation before doing a layer of gas reservoir. In the past, plastic sheeting was used in construction, and most of the formal cold storage systems were made of cyanide gas;
      Two, ground construction method: the ground adopts two layers of 8cm Extrusion board, according to the wrong seam paving
      The first waterproof layer (plastic) and Pu XPS extruded boards, each side seam, about 2 cm, and then using polyurethane adhesive sealing requirements, flat polyurethane material Tim plastic extruded board is not higher than XPS.
      Three 、 wall panel and top panel construction method
      The two layer 8cm board in accordance with staggered Putie surface spraying polyurethane 3 cm
      First, a layer of 8cm Extrusion board is directly adhered to the wall, and then 10cm plastic expansion screws are used to fix 3-4 expansion nails per square meter. Then, each side of the Extrusion board is filled with polyurethane. The second layer 8cm
      Polyurethane adhesive for extrusion plate. The outer surface of the coating is 3 cm polyurethane as sealing layer.

              

      Thermal insulation construction scheme of high temperature storehouseAccording to the thermal conductivity of XPS extruded insulation board is 0.027 and the temperature requirement of high temperature warehouse is 0 degrees, the following methods are adopted for construction:
      First, the warehouse wall and roof insulation before doing a layer of gas barrier, the use of cyanide condensate gas barrier, to prevent the entry of water vapor, water directly into the cold storage insulation effect failure;
      Two. Ground construction method
      The floor is made of two layers of 5cm extruded board, which is laid on the wrong seam
      The first waterproof layer (plastic), a layer of plastic cloth, wall thickness of 0.018, then spread XPS extruded insulation board, each side seam, using polyurethane adhesive sealing requirements, flat polyurethane material Tim plastic extruded board is not higher than XPS.
      Three 、 wall panel construction method
      The wall panel is made of two layers of 5cm extruded board and laid on the wrong seam
      Put a layer of 5cm extruded plate directly pasted on the wall, then 10cm plastic expansion nail fixed by 3-4 per square expansion nail, then each side with extruded plate polyurethane pouring adhesive; second layer 5cm board with polyurethane glue staggered paste.
      Four 、 top construction method
      The roof construction: put a layer of 8 cm of extruded plate hoisting in I-shaped steel beam, and from inside the 3 cm polyurethane sealing coating.